Funds for Watergate Common Area Renovations and Building Fire Suppression will come from WCA reserves. No special assessment is planned or expected.
Common Area Renovations and Signs News
Watergate has entered into a design services agreement with Huntsman Architectural Group for the enhancement and renovation of the common use areas. The design development process is currently underway with final design approval and renovation work expected to commence Winter 2011.
Please contact construction manager Gus Ferriols for information regarding all Watergate replacement and renovation projects.
Completed/Upcoming Projects
→Code Pool Fencing Surrounding Clipper Club Main Pool--November 2008 - Completed →Tennis Pro Shop Roof Replacement--November 2008 - Completed →Anchor Drive Repaving--May/June 2009 - Completed
→Anchor Pool Replastering--August 10, 2009 through October 19, 2009 - Completed →Clipper Club Pool Heater Replacement--February 2010 (Funding approved 12/14/2009) - Completed
→Boardwalk Railing Replacement--January through March 19, 2010 (Funding approved 12/14/2009) - Completed
→Anchor Spa Rebuild and Club Renovations--Mid-January through March 26, 2010 (Funding approved 12/14/2009) - Completed
→Resurface Tennis Courts--June 28, 2010 through July 9, 2010 (Funding approved 5/25/2010)
→CARS Prototype -- Tentatively scheduled for August/September 2010 (Funding Approved June 21, 2010) →Lobby and Common Area Key Access Change Out--Winter/Spring 2011
→Fire Suppression--Fall 2010 through Fall 2015 (E - 2010, C - 2011, A - 2012, D - 2013, B - 2014 and F - 2015)
→Interior Renovations--Winter 2011 through Winter 2016 (E - 2011, C - 2012, A - 2013, D - 2014, B - 2015 and F - 2016)
All replacement project funding and project schedules and are subject to board approval.